R/O Shops, 9-19 Manor Green
Road, Epsom,
Surrey KT19 8RA
Installation Instructions Basic Indrect Heat Bank Thermal Store
3339-1 12/02/01
Heat Bank Thermal Store System Everest combination unit Single Heat Exchanger (30 ltr/min) Indirect 35mm Foam Insulation High duty primary coil Boss 1/2" For Immersion Cylinder Stat All fitted controls are wired Thermostatic Blending Valve 22mm Backup Immersion Heater
1 Integral Feed & Expansion Tank 2 Plate Heat Exchanger 3 Heat Exchanger Pump 4 Flow Switch 5 Thermostatic Blending Valve, Mixcall III 6 Manual Air Vent 8 Filling Vent 9 Feed to Ball Valve 10 Isolating Valve 11 Y-Pattern Strainer (supplied loose) 12 Overflow (supplied loose) 13 Cold Feed / Expansion 14 Immersion Heater 3kW Incaloy with Stat 16 Cold Mains In, 22mm 17 Hot Mains Out, 22mm 18 Drain Cock 21 Flow to Primary Coil 22 Return from Primary Coil 40 Tight Fitting Lid 42 Wiring Centre